Point in time (particular date) for transition from construction to operations. The COD can be calculated in different ways. For example, it could be defined as the point in time when the last WTG gets into operations or the average of the CODs of all WTGs. Before COD, there is usually a final walk-through and short test period (e.g. 240 hours without stop).